Project Summary | Planned | Status | ||||||
Project ID | Title | Sponsor | Start | Finish | Budget | Scope | Schedule | |
1401 | Digital Services (Website) | Communications & Member Relations | Jan ’14 | Mar ’14 | £4,000 | Complete | Complete | |
1402 | Core Communications (E-mail) | Communications & Member Relations | Jan ’14 | Feb ’14 | £500 | Complete | Complete | |
1403 | Information Access (Documents) | Communications & Member Relations | Jan ’14 | Mar ’14 | £500 | Complete | Complete | |
1404 | Governance Review | Chairperson | Feb ’14 | Apr ’14 | £0 | Complete | Complete | |
1405 | Accounts Analysis | Finance | Jan ’14 | Feb ’14 | £0 | Complete | Complete | |
1406 | Managing Agent (Recontracing) | Operations | Feb ’14 | Dec ’14 | £0 | Complete | Complete | |
1407 | LVT Test Case Support | Company Secretary | Rejected | |||||
1408 | Marketing & Brand Review | Chairperson | Deferred | tbc* | ||||
1409 | Site Services Review | Chairperson | Jul ’14 | Sep ’14 | £0 | Complete | Complete | |
1410 | External Cleaning Project | Operations | Deferred | tbc* | ||||
1411 | Lighting Renewal Project | Operations | Apr ’14 | Apr ’15 | £65k + | Green | Green | |
1412 | Digitising Assets Project | Company Secretary | Apr ’14 | Jun ’14 | £2,500 | Complete | Complete | |
1413 | Maintenance Planning | Operations | Deferred | tbc* | ||||
*deferred projects are unable to be progressed until funds currently locked through litigation are made available to VHMC.